Hormozgan 1” 500-megatwatt gas-run power plant

12 خرداد 1387 11:07

To develop the electricity generation capacity of the nation and meet an ever-increasing demand in the south, the Iranian Electricity Development Organization decided to build the “Hormozgan 1” power plant which has 4 gas-run units, each with a capacity of 165 megawatts (500 megawatts in total).

Future prospect of the country’s hydroelectric energy development

31 ارديبهشت 1387 11:43

Due to the existence of the three Karun, Dez and Karkhe rivers in Khuzestan Province, this company’s main activities are concentrated on this region. However, projects are being implemented and studied in Chahmahal and Bakhtiari, Lorestan and Ilam provinces.

31 ارديبهشت 1387 11:03

During 1967 – 1992 initial studies were carried out on the construction of a dam between the city of Gotvand and Masjed Soleyman Dam and a number of proposals were made.

Sivand Dam

21 ارديبهشت 1387 11:58

Some 55 years ago, the American Justin Courtney started his studies on the Sivand Dam and according to those studies the site of the dam had to be at this point. In 1988, the Seko Engineering Company was tasked with completing Courtney’s studies that took until 1994.

10 ارديبهشت 1387 9:22

In order to implement the policies of the country’s Five-Year Development Plan and the necessity to supply electricity to strengthen the country’s national grid, the construction of the gas sectors of new combined-cycle power plants was handed over to the Iran Electricity Development Company in ...

8 ارديبهشت 1387 10:43

Initial studies were carried out of the project by Tractionell Consultant, a Belgian Company, in 1970. The first phase studies were completed in 1972 by the same company.

Iran-funded project in Sri Lanka to become operational

8 ارديبهشت 1387 10:18

Iran-funded multi-purpose Uma Oya Project will commence on Tuesday when the President of the Islamic Republic of Iran Mahmoud Ahmadinejad and President Mahinda Rajapaksa ceremonially inaugurate the mega development project in Sri Lanka.

Mollasadra Dam and Power Plant

7 ارديبهشت 1387 10:51

Considering that the construction of the Mollasadra Dam and Power Plant has reached its final stage and the dam will become operational in the near future, we have decided to introduce the specifications of the dam in this issue

Masjid Soleyman Dam

13 بهمن 1386 8:55

The history of the hydroelectric development of the Karun River dates back to 1961-1970. At that time a series of studies were carried out on the Karun River basin in order to identify the possibilities to develop this river’s water resources. Following feasibility studies in 1990, a decision was ...

Kuhrang Dam

6 بهمن 1386 10:30

Zayand-e Rud (Zayand-e River), which is the largest and most important river in central Iran, originates from Zard Kuh, situated on the Zagros mountain range. After passing the west of the country, this river runs towards Esfahan and joins the Gavkhuni marshlands in the south of the city of Yazd.

1 بهمن 1386 15:18

Following an initial agreement approved by the Tavanir Company on 17 August 2000, and based on Note B of Article 122 of the Third Development Plan, the Aryan Mahtab Company was permitted to start work on the construction of a 2000 KW power plant alongside the 400 KW Rud-e Shur electricity outpost.

28 آذر 1386 11:21

Expert studies on the Dareh Rud river basin began in 1989 and following the approval of the subsequent reports, projects for the construction of a dam in that region were drawn up in 1993. In continuation of these studies, consultant engineers began studies on the first and second phases of Sabalan ...